SOUTHERN PALLADIUM LIMITED - Bengwenyama Update: DFS Works Program Advancing with 6,651m Drilling Completed Alongside Mine Design Optimisation

Southern Palladium Limited
Free preview

What this filing means

Bull case

  • Phase 2 DFS drilling is 49% complete and on schedule for the August 2026 target.
  • Mine design optimization to a 9° decline gradient reduces total development metres and shortens the box cut.

Bear case

  • The shift to a steeper 9° decline gradient introduces potential operational risks compared to the original 6° plan.
View original SENS announcement

AI-generated summary by SENS-AI, based on the original JSE SENS filing.